Lion's Head Sidewalk Reconstruction - Phase #2
Project Details: The Municipality of Northern Bruce Peninsula is undertaking a construction project in your area. This letter provides details about the project and information on how the project may affect you and your household.
Location: East side of Main Street Lion’s Head (County Road #29) from Scott Street South to Moore
Street and on the West Side of Main Street (County Road #29) from Edgewood Street South to Moore Street.
Schedule:
Start Date: April 7, 2025 (weather pendant)
Finish Date: May 30, 2025
Working Hours: Monday – Thursday 7:00 am – 7:00 pm; Friday – 7:00 am – 6: 00pm; Saturday/Sunday – 7:00 am- 6:00pm
Scope: Remove existing Interlock Pavers, Supply/Install/Compact Granular Material, Form & Pour Sidewalks, Curbs in specified areas only, Ramps and Steps as needed, Provide Curb Repairs & Asphalt Repairs, Topsoil and Sod Restoration.
Consultant: GSS Engineering Consultants Ltd.
Contractor: Signature Contractors (Windsor) Inc